Catteshall Lane – Housing Development Groundworks

SECTOR 
Housing Groundworks, Infrastructure & 278 Works
OUR ROLE
Subcontractor
LOCATION
Godalming
CLIENT
Crest Southern
PROJECT VALUE
£5m
DURATION
2 years

OVERVIEW

This project comprised the delivery of the housing development groundworks and infrastructure for a new 97-unit residential housing development located at Catteshall Lane, Godalming, for Crest Southern. Natta was appointed to undertake the early and enabling phases of the works, preparing a complex and constrained site for future housing construction.

SCOPE OF WORKS 

The project was particularly challenging due to a 10-metre fall across the site, which required careful consideration of levels, stability, and sequencing of works. In addition to the steep topography, the site was affected by extensive contamination, including a mixture of metals, asbestos, hydrocarbons, peat, solvents, and the presence of multiple aquifers. These conditions required comprehensive over-pumping as well as strict control measures to ensure safe and compliant working.

Natta successfully managed the initial decontamination phase, implementing appropriate remediation strategies to address the contaminated materials and groundwater conditions. Subsequently, this critical stage made the site safe and suitable for onward development.

As part of the infrastructure works, Natta also delivered the installation of retaining walls to both the secondary and main roads, providing long-term stability across the varying site levels. In addition, the project included the installation of drainage infrastructure, ensuring effective surface and groundwater management in line with engineering and environmental requirements. As the enabling works were completed, the site reverted to a standard housing groundworks site, subsequently allowing the residential construction phase to proceed.

Natta secured this project through our historical expertise in remediation and our proven capability to manage complex, high-risk ground conditions. As a result of this experience, we were able to take on the site risk, delivering a safe, compliant, and successful outcome for the development.

Natta Building GDRP Logos
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Cookie Policy

If you leave a comment on our site you may opt-in to save your name, email address and website in cookies. These are for your convenience so that you do not have to fill in your details again when you leave another comment. These cookies will last for one year. If you have an account and you log in to this site, we will set a temporary cookie to determine if your browser accepts cookies. This cookie contains no personal data and is discarded when you close your browser. When you log in, we will also set up several cookies to save your login information and your screen display choices. Login cookies last for two days, and screen options cookies last for a year. If you select “Remember Me”, your login will persist for two weeks. If you log out of your account, the login cookies will be removed. If you edit or publish an article, an additional cookie will be saved in your browser. This cookie includes no personal data and simply indicates the post ID of the article you just edited. It expires after 1 day.

Read more - Privacy Policy