b'Project FactsOverview: This project is for the groundworks and infrastructure to 110 Sector: Infrastructurehouses at the former MOD Base at Arborfield. Our Role: Sub Contractor Scope of Works:Location: ArborfieldWe undertook the full build to DPC including CFA piled foundations, Client: Crest Nicholsonsubstructure blockwork and block and beam floors and issuing collateral warranties to the developer.Project Value: 6mThe aggressive build programme has entailed a workforce of some 50 operatives to undertake work on a number of different fronts at the same Duration: 20 monthstime.As our extended remit we acted as principal contractor until the developer was able to take over.'