b'CopthorneInfrastructure SECTOR:OVERVIEW: Infrastructure & 278A new roundabout and access road to service a major 500 unit Workshousing scheme with associated community amenities and commercial units. OUR ROLE: SCOPE OF WORKS: Main Contractor As Principal Contractor, we were awarded the initial contract to construct the large new 278 roundabout and access off the existing LOCATION:A264. Copthorne, Crawley Considerable earthworks cut and fill was required in challenging soil CLIENT:conditions as the area was previously used as an inert material tip. St ModwenAn on-site lab was set up to conduct the geo-technical testing and Developmentsour experience in this field has lead to a successful delivery and acceptance from West Sussex County Council. PROJECT VALUE: 8mThe project also includes a new bridge, prefabricated portal sections used to save programme, installation of a large 2.10 m DURATION:diameter attenuation pipe together with new services and drainage. 15 monthsSee next page for more'