Oak Grove Phase 5

Milton Keynes
  • Milton Keynes
  • Milton Keynes
  • Milton Keynes
  • Milton Keynes
  • Milton Keynes

Project Facts

  • Sector:

    Civil Engineering, Infrastructure & 278 Works

  • Our Role:

    Sub Contractor

  • Location:

    Milton Keynes

  • Client:

    Crest Nicholson Regeneration

  • Project Value:

    £5m

  • Duration:

    2 years

Overview:

This project is for the groundworks to a 73 unit housing site.

Scope of Works:

Our works include the associated roads, sewers, piled foundations up to and including floors, drives, sheet lighting and landscaping.

The particular challenge was removing a 45,000m³ heap of soil that had built up from the previous 4 phases of the development and installing a 215m long gabion retaining wall, whilst maintaining progress on the initial site build.

The site is progressing well and is due to be completed in 2019.