Oak Grove Phase 5
Milton Keynes
Project Facts
-
Sector:
Civil Engineering, Infrastructure & 278 Works
-
Our Role:
Sub Contractor
-
Location:
Milton Keynes
-
Client:
Crest Nicholson Regeneration
-
Project Value:
£5m
-
Duration:
2 years
Overview:
This project is for the groundworks to a 73 unit housing site.
Scope of Works:
Our works include the associated roads, sewers, piled foundations up to and including floors, drives, sheet lighting and landscaping.
The particular challenge was removing a 45,000m³ heap of soil that had built up from the previous 4 phases of the development and installing a 215m long gabion retaining wall, whilst maintaining progress on the initial site build.
The site is progressing well and is due to be completed in 2019.