Mill Road
Mill Road, Hertford
Project Facts
-
Sector:
Basements, Civil Engineering
-
Our Role:
Sub Contractor
-
Location:
Mill Road, Hertford
-
Client:
Redrow Homes
-
Project Value:
£2.5m
-
Duration:
12 months
Overview:
This project has two distinct parts: a reinforced concrete basement and podium slab, together with a traditional housing site, roads and sewers external works.
Scope of Works:
All of the site was piled; the ground had contamination. Our package for the basement and podium slab included provision of a Tower Crane.
The site was adjacent to Hertford Train Station and two busy roads, which constrained access and crane positioning.
The Reinforced Concrete works were completed 4 weeks ahead of programme.