Hertford

Hertfordshire
  • Hertford
  • Hertford
  • Hertford
  • Hertford

Project Facts

  • Sector:

    Basements, Building, Groundworks

  • Our Role:

    Sub Contractor

  • Location:

    Hertfordshire

  • Client:

    Weston Homes

  • Project Value:

    £3m

  • Duration:

    24 months

Overview:

 
The works consisted of a waterproof concrete basement with transfer slab. Together with associated 278 road works, storm water attenuation, external hard landscaping and underpinning.

Scope of Works:

The site had particular constraints working adjacent to the river Lea and retaining the existing highway which sat some 4 metres above river level.

The works were phased to quickly follow the demolition of the existing buildings and required close coordination with all of the stakeholders.