Children's Centre, Westbourne Green, London

Project Facts
Sector: RC Frames
Our Role: Sub Contractor
Location: Westbourne Green, London
Client: Speller Metcalfe
Project Value: £400,000
Duration: 24 weeks
Overview:
A turnkey project to construct a multi storey reinforced concrete frame building as a childrens centre for the City of Westminster Council on a restricted inner city site.
Scope of Works:

Natta were employed to carry out the following works erection of site hoarding. Demolition of the existing structure and reduced level excavation. Placing of piling mat and piling and the excavation, cutting down of piles and constructing pile caps. The construction of a retaining wall and suspended ground floor slab. All associated drainage works and services to the building. Construction of a three storey reinforced concrete frame. Provision of Natta’s own craneage to carry out the works.

PROJECT ACHIEVEMENTS

"This statement circular frame and basement turnkey project won an award which the whole team take pride in."

Andy Fowler Contract Manager Natta
print