modern thinking
traditional values

Residential Development, Edgware

Project Facts
Sector: Basements
Our Role: Sub Contractor
Location: Edgware, London
Client: Weston Homes
Project Value: £3.4 m
Duration: 24 months
Overview:
The site consisted of a reinforced waterproof concrete basement and podium slab, together with ancillary housing blocks.
Scope of Works:

The site required extensive earthworks and kingpost support systems to the perimeter.

Our works extended to undertaking superstructure concreting for progressive collapse requiring close co-ordination with other trades. Access for plant and deliveries was limited and required careful management with other trades.

PROJECT ACHIEVEMENTS

"Natta managed and overcame the issues with the conjested, restricted access to the project and delivered the works to a high standard and on programme."

Nick Loizou Quantity Surveyor NATTA
print